We are ready to begin the reconstruction of the factory building – all 43 columns and installation materials have been delivered. We are now waiting for temperatures to rise to a level suitable for construction work.
“Winter has slightly delayed the start of our work, as technologically the columns can only be installed at temperatures no lower than -5°C. The columns were delivered before Christmas, but a cold spell began right away, so we’ve had to wait for more favourable weather. Still, we expect the cold to end soon and to get started,” says Algirdas Blazgys, CEO of our company.
Construction experts have assessed that 43 columns need to be replaced. Over the summer and autumn, the old columns were dismantled and the foundations prepared for the installation of new ones.
We want to thank Kauno Perdanga for manufacturing and delivering the reinforced concrete columns on time.
Once the columns are replaced, we will proceed with installing the roof and walls, which are already in production. After that, the installation of new equipment will follow.
The factory is set for a full-scale upgrade this year, ensuring that waste in the Vilnius region is handled using modern, innovative solutions.